Installation

Your proposal for an Alfresco Room installation will be supported by an initial survey to establish suitability, precise location and orientation, source of services, drainage and access detail. The foundation structure would be determined by the pre-existing sub-strata, and it may be necessary to undertake further explorative action if this is unknown.

A full specification will be drawn up and presented for your approval. This document will then serve as the basis for planning applications and for progressing your order. Your personal account manager will then contact the specialist tradesmen to coordinate their site presence with the timely arrival of your Alfresco package. Assuming planning approval is in place, and depending upon your selected model and inclusions, it is intended that the schedule of works for a standard specification would be expected to run as follows:

Excavation + oversite preparatory works: 3 days
Foundations build-up & minimum cure 2 + 3 days*
Structure assembly/electrics/Climate pack 4 - 5 days
Internal screed 1 day
Completion of glazing and clean-up 1 day

*Weather dependent

 

All installation work is undertaken by bona-fide trade professionals, and safety measures are governed by risk assessment and method statement.

 

Foundation design: RWCL Chartered Civil Engineers
Structures: Able Canopies Ltd
Electrical installations: NICEIC
Climate Package: ACRIB

 

Back to > Alfresco Rooms Modular Building

Canopy | Canopies | Shade Sails | Sun Canopies | Walkways | Cycle Shelters | Waiting Shelters | Entrance Canopies | Modular Buildings | Window Film | Awnings

Outdoor Canopies | Shade Canopies | Sun Canopies | Shade Sails | Bike Shelters | Canopies for Schools

Call Able Canopies free on 0800 389 9072 or email sales@ablecanopies.co.uk

SiteWizard.co.uk Website Design | eCommerce Software Shopping Cart Solutions | SEO by Leonardo Wood SEO Tips